It's been an incredible month of progress!
Utilities and infrastructure:
The well house is now fully framed, insulated, and drywalled. The well equipment has been hooked up, and we officially have running water. Permanent power has been successfully connected to the main church building.
Interior work:
Interior walls are insulated, and ductwork has been sealed and insulated with spray foam. Drywall insulation is complete across most of the building, with only the dining room, narthex, and office remaining. Drywall taping is scheduled to begin next week.
Exterior:
The metal cross has been installed, the fire tank cover is in place, and the fire tank house is now framed. Siding installation is complete and freshly painted. All exterior concrete has been poured. Block work for the sign column is now finished.