On Friday, May 8th, the concrete floor pour began at 5:00 am with a large turnout of volunteers. The main pour was completed by 10:00 am; the finishing work and control joints were finalized by the end of the day. In addition to the main floor pour, the crews poured six parking lot light footings as well as the front entry footings and columns, utilizing a total of 230 cubic yards of concrete. This is a major milestone in the project. Now framing can begin!
Welcome to the Flathead Valley Laestadian Lutheran Church building project update page. After several years of prayerful discussions and planning, our church build has begun. We saw a lot of progress right away in the last week of March with excavating, connecting power, forming footings, pouring the footings, tying steel rebar for foundation, and installing forms for the foundation walls. It was exciting to see such progress in just a few days. With willing and energetic workers, the footings were complete. Not only were the men busy working, we are thankful for the ladies in the congregation for preparing and delivering meals and snacks to the crew on site.