Over the last couple weeks, we have made steady progress on the foundation despite variable weather. The foundation walls are insulated, and both the exterior and interior of the building have been backfilled. Additionally, the under-slab plumbing is complete and backfilled. We are currently holding off on floor preparation due to the recent cold and snow in the valley; we will resume as soon as the weather improves to proceed with the concrete pour.
Welcome to the Flathead Valley Laestadian Lutheran Church building project update page. After several years of prayerful discussions and planning, our church build has begun. We saw a lot of progress right away in the last week of March with excavating, connecting power, forming footings, pouring the footings, tying steel rebar for foundation, and installing forms for the foundation walls. It was exciting to see such progress in just a few days. With willing and energetic workers, the footings were complete. Not only were the men busy working, we are thankful for the ladies in the congregation for preparing and delivering meals and snacks to the crew on site.